WBHO (Asanko Gold Mines)

WBHO (Asanko Gold Mines)

Client:

WBHO

Services:

Construction of a Man Camp Facility

Date:

Not Available

Website:

Not Available

Project Overview

Kat Engineering Ltd was contracted by WBHO to undertake the Construction of a Man Camp Facility at Asanko Gold Mines. The project was designed to provide modern accommodation and supporting infrastructure for mining personnel, ensuring safety, comfort, and operational efficiency.

Scope of Works

  • Earthworks – Site clearing, excavation, grading, and compaction for camp foundations.
  • Concrete Works – Reinforced concrete foundations, slabs, and structural elements for housing and communal facilities.
  • Installation of Camp Houses – Prefabricated housing units installed and fitted with utilities, including water, sanitation, and electrical systems.
  • Supporting Infrastructure – Access roads, drainage, and utility connections to integrate the camp into the mine’s operations.

Commitment

This project demonstrates Kat Engineering’s ability to deliver comprehensive construction solutions in mining infrastructure. By combining technical expertise, modern construction methods, and transparent project management, Kat Engineering continues to embrace challenges and provide sustainable solutions that support resource development projects.